S3 EXCAVATION WORKS: FROM 7 AUGUST

loading...
Posted: Thursday 6th August 2020

From 7 August we will be excavating a trench from the footpath outside Victoria Hall and Moss Pilates and across Canal Reach. These works are taking place to install two heating pipes and a gas pipe across Canal Reach for the new S3 Building development and will last approximately 5 weeks.

Works will take place behind acoustic barriers to minimise noise disruption and access will be maintained on the footpath and road at all times.

King’s Cross apologise for any inconvenience caused.