Maintenance works on gas pipes: 28 October to 9 December

Posted: Thursday 24th October 2019

Maintenance works on gas pipes will be taking place around the site from Monday 28 October to Monday 9 December.

The works will take place in the following locations between the following dates: 

  • 28 October – 4 November: On the ramp next to Tom Dixon
  • 4-11 November: In front of 2 Pancras Square on King’s Boulevard
  • 11-18 November: Between the Underground entrance and Nike on King’s Boulevard 
  • 18-25 November: To the rear of the German Gymnasium
  • 25 November -2 December: By 7 Pancras Square and to the rear of 4 Pancras Square on Goods Way
  • 2-9 December: Just off Granary Square, to the rear of The Lighterman

Each set of works will take one week to complete. A temporary finish will be put in place until all these works complete when permanent paving will be installed. 

The works should not be noisy and there will be minimal disruption to residents. There will be some pedestrian diversions in place on King’s Boulevard while the works are carried out, and these will be clearly sign posted.

King’s Cross apologise for any inconvenience these works may cause

Contact Us

For more information about the development at King’s Cross, please visit the King’s Cross Visitor Centre. Mon-Fri 10-5pm, Sat, 10-4pm.

For all other enquiries please call our Freephone Helpline 0800 328 8840 or email the construction help desk

Good neighbours

We aim to minimise the impact of construction. Find out more about how we do this.

Jobs in Construction

Are you looking to work in construction? The Construction Skills Centre at King’s Cross can help.

Our website uses ‘cookies’ to give you the best, most relevant experience. If you continue without changing your settings we’ll assume you are happy to receive cookies on our website. However, you can change your cookie settings at any time.