Tower crane works at A Zone

Posted: Monday 12th August 2019

A number of tower cranes will be installed and dismantled at A Zone, set to be Google’s UK headquarters, over the coming months, as construction progresses on site.

These works will take place over the weekend as this is a high risk activity and cannot be undertaken during normal working hours.

The works are taking place from 8am-5pm over the following weekends:

  • TC5 install: 31 August – 1 September
  • TC7 removal: 14 – 15 September
  • TC4 install: 12 – 13 October

All activity will be within the hoarding line on the site compound. No mobile cranes will need to be brought to site in order for these works to take place.

King’s Cross apologise for any inconvenience these works may cause.

Contact Us

For more information about the development at King’s Cross, please visit the King’s Cross Visitor Centre. Mon-Fri 10-5pm, Sat, 10-4pm.

For all other enquiries please call our Freephone Helpline 0800 328 8840 or email the construction help desk

Good neighbours

We aim to minimise the impact of construction. Find out more about how we do this.

Jobs in Construction

Are you looking to work in construction? The Construction Skills Centre at King’s Cross can help.

Our website uses ‘cookies’ to give you the best, most relevant experience. If you continue without changing your settings we’ll assume you are happy to receive cookies on our website. However, you can change your cookie settings at any time.