Out of hours works at Q Zone on Saturdays: 1 June – 20 July

loading...
Posted: Thursday 23rd May 2019

From Saturday 1 June until Saturday 20 July, the contractors at Q Zone will be extending their working hours on Saturdays so works will take place between 8am and 5pm. No noisy works will take place after 1pm. The purpose of this is to complete ground works above the Network Rail Gasworks tunnels and to ensure the tunnels are adequately loaded.

King’s Cross apologise for any inconvenience caused by these works.