T Zone Construction Works Commence End July 2018

Posted: Thursday 26th July 2018

Construction work on the remaining plots on the T Zone (11 & 21 Canal Reach) will commence on 30 July 2018 with piling works.

These works will take place within normal construction hours and will take a total period of 16 weeks – working from south to north of the site.

Once piling has been completed a total of 4 no. tower cranes will be erected on site to allow the construction of the buildings to commence.

King’s Cross apologise for the inconvenience these works may cause.

Contact Us

For more information about the development at King’s Cross, please visit the King’s Cross Visitor Centre. Mon-Fri 10-5pm, Sat, 10-4pm.

For all other enquiries please call our Freephone Helpline 0800 328 8840 or email the construction help desk

Good neighbours

We aim to minimise the impact of construction. Find out more about how we do this.

Jobs in Construction

Are you looking to work in construction? The Construction Skills Centre at King’s Cross can help.

Our website uses ‘cookies’ to give you the best, most relevant experience. If you continue without changing your settings we’ll assume you are happy to receive cookies on our website. However, you can change your cookie settings at any time.